Mold change time
Mold changes are at the goal at the first two presses, and the rest of the plant has not started.
- Status
- Going well
| What happened | At two presses, the next mold's hoses and tools now wait on a cart before the press stops. Every cart was loaded in time this week, and both had their fastest week. |
| Why | Each shift's supervisor named the changes due, so every cart was loaded from its checklist while the old job still ran. |
| Since last week | Last week's issue is fixed: the slow press had its cart loaded ahead every time and now matches the other. |
| How to keep it up | Keep naming the changes due at each shift start, and bring the other four carts into use. |
| Owner | Setup lead |