Why it works
| Mechanism | - A part can come out once its thickest wall is stiff enough to keep its shape.
- Each second the mold stays shut after that makes nothing.
- A shorter timer ends each cycle sooner, so the same job needs fewer press hours.
|
| Math | - The five longest-running jobs ran about 18,000 press hours in twelve months, at an average cycle of 30 seconds.
- One second off each cycle frees about 600 of those hours.
- We assume orders fill 70 percent of them, 420 hours, and each filled hour earns $55: about $23,100 per year.
- The trials cost about $2,100 once: five jobs at about 8 hours each of a process technician, at $52 an hour.
- That pays back in about 1 month.
|
| Industry evidence | - In published cases of shorter molding cycles, cooling is often 60 to 80 percent of the cycle.
- Molding handbooks give a standard formula: the cooling time a part needs rises with the square of its thickest wall.
- So each timer can be checked against its part.
- No published figure gives the spare time in cooling timers, so the seconds here are our estimate.
|
| Limitations | - A freed press hour earns money only if an order fills it.
- A round number is only a sign, so some timers may already be right.
- A timer cut too far lets a part warp after it leaves the press, so each step is checked on cold parts.
- A part whose process a customer approved waits for the customer's sign-off, which can take four to twelve weeks.
- And where the press needs that time to melt plastic for the next shot, a shorter timer saves nothing.
|
Illustrative sample. The plant, the walk and the footage are synthetic. Figures from our analysis are estimates made with AI, not guarantees.