Pythia Industries

Sample Plant

Evidence

Orders due over the week, shipped on time and shipped late

The ERP compares the promised date and the ship date of each order due from Sep 7 to Sep 11. 38 of the 41 shipped by their promised date, above the plant's best earlier week of 92 percent.

Shipping, Sep 7 to Sep 11, ERP shipping record

From the plant's ERP
Orders due from Sep 7 to Sep 11Count
Due41
Shipped on time38
Shipped late3
Share shipped on time93 percent

How the queue at welding came down over the week

The ERP counts the sets of parts waiting to be welded and how many days of work that adds up to. The queue held at about 9,000 until the evening shift started welding, then fell by about 3,000 a day.

Ultrasonic welding, Sep 7 to Sep 10, ERP job log

From the plant's ERP
DateCounted atSets of parts waitingDays of work waiting
Sep 7Start of day shift9,0003 days
Sep 8Start of day shift9,0003 days
Sep 8End of evening shift6,0002 days
Sep 9End of evening shift3,0001 day
Sep 10End of day shift1,500Half a day

Illustrative sample. The plant, the walk and the footage are synthetic. Figures from our analysis are estimates made with AI, not guarantees.