Evidence
The last shift start of the week, bin emptied and dryer hot
The scrap bin beside the press is emptied as the Sep 11 night shift starts, and the dryer is full and hot. The camera shows the same at all fifteen shift starts since Sep 7, which removes the two usual causes of stops.
Press 3, Sep 11, 10:02 pm, Camera 2
Hours run each day of the week against the schedule
The ERP shows how many hours the press was scheduled to run each day and how many it actually ran. No day shows an unplanned stop, and the 2 missing hours on Sep 10 were a planned mold cleaning.
Press 3, Sep 7 to Sep 11, ERP run records
| Date | Scheduled to run | Ran | Unplanned stops |
|---|---|---|---|
| Sep 7 | 24 hours | 24 hours | None |
| Sep 8 | 24 hours | 24 hours | None |
| Sep 9 | 24 hours | 24 hours | None |
| Sep 10 | 24 hours | 22 hours | None |
| Sep 11 | 24 hours | 24 hours | None |
| Sep 7 to Sep 11 | 120 hours | 118 hours | None |