How the pile of parts waiting to be welded shrank each day

The ERP counts the sets of parts waiting to be welded and how many days of work that adds up to. The queue held at about 9,000 until the evening shift started welding, then fell by about 3,000 a day.

Ultrasonic welding, Sep 7 to Sep 9, ERP job log

From the plant's ERP
DateCounted atSets of parts waitingDays of work waiting
Sep 7Start of day shift9,0003 days
Sep 8Start of day shift9,0003 days
Sep 8End of evening shift6,0002 days
Sep 9End of evening shift3,0001 day

The second welding machine back at work on a second evening

The second welding machine runs again on the evening shift, with parts fed in from the carts beside it. It ran a second evening, and at the end of that shift the count was about 3,000 lower than a day earlier.

Ultrasonic welding, Sep 9, 9:40 pm, Camera 10

Illustrative sample. The plant, the walk and the footage are synthetic. Figures from our analysis are estimates made with AI, not guarantees.